Work centers
Loading content & screenshots...
Work centers are where Manufacturing work orders are processed, and can be used to track costs, make
schedules, plan capacity, organize equipment, and track efficiency.
Specifying a work center is required when a work order is defined in
the Operations tab of a bill of materials (BoM) for a product.
Enable work center
Work centers only appear if the Work Orders
setting is enabled. To do so, navigate to , then tick the Work Orders checkbox. Work orders can be managed in the Manufacturing
app by selecting .
Create a new work center
In the Manufacturing , go to select
and click the Create button to open a new work center
form.
The General Information tab on the work center form allows for productivity goals to be assigned to a work center. These are used as the basis for calculating how much of the potential time the work center is being used and its operating costs.
Work Center Name: the label for the work center used to select it on a work order or on the reporting dashboards
Alternative Workcenters: where a work order should be carried out if this work center is not available
Code: reference id for the work center that is displayed in the list view
Working Hours: the hours that work center can be used during the week
Time Efficiency: a multiplier for how using this work center affects the normal speed of execution of a work order
Example
If a work center has older equipment and work orders take twice as long to produce, the Time Efficiency would be 50.00%.
If a work center has older equipment and work orders take twice as long to produce, the
Time Efficiency would be 50.00%.Capacity: the number of products that can be processed at the work center simultaneously
OEE Target: the target for efficiency at the work center
If a work center is available for8 hours per daybut is only expected to be used for7 hours per day, the OEE would be87.50%.